Green Rigg

Client:

Waitings

Contract period:

1 Week (July 2012)

Contract Value:

£120,000

Scope of Works:

To carry out surfacing to a U road which has protected verges and no passing places within 2k. The road was 3300m long and a logistical struggle. DSD managed to knock 2 days off the programme to ensure the local farmers could carry on with their jobs and not be held up with our operations. Our efforts were commended by the local Council for the quality and speed of our work. No verges were damaged in the course of our works and once again we left some very satisfied customers.