A596 Thursby to Workington

Client:

Balfour Beatty / Connect Roads

Contract period:

8 weeks (May – July 2012)

Contract Value:

£320,000

Scope of Works:

To carry out cold milling and re-surfacing in various locations along the A596 Thursby to Workington. All Wearing Course used within the scheme was Cl942 SMA.

Work was completed to budget within a tight programme period with restrictive site working hours. It was also interfaced and co-ordinated with external traffic management and road marking crews.