Barr Sainsburys Carlisle

Barr-Sainsburys-020512-006-Medium

Client:

Barr Construction

Contract period:

3 Weeks in-between (May – September 2012)

Contract Value:

£260, 000

Scope of Works:

To carry out surfacing work to new formation including Car Parks, Haul Roads and Footways. Due to such a tight programme the site is a very busy place, therefore interface with all contractors is critical to meeting our deadlines.

Work is ongoing but being completed to budget within a tight programme period.

A596 Thursby to Workington
Preston East
 

Comments

No comments made yet. Be the first to submit a comment
Guest
Sunday, 22 September 2019